30. At any time before rendering a decision, the adjudicator may request complementary information and additional documents from the parties.
If the adjudicator considers it useful to do so, he or she may also request supplementary information from the public body that entered into the public contract or from any other enterprise that is a party to a public subcontract related to the public contract; they must provide the information to the adjudicator within the time specified.
M.O. 2018-01, s. 30.
In force: 2018-08-02
30. At any time before rendering a decision, the adjudicator may request complementary information and additional documents from the parties.
If the adjudicator considers it useful to do so, he or she may also request supplementary information from the public body that entered into the public contract or from any other enterprise that is a party to a public subcontract related to the public contract; they must provide the information to the adjudicator within the time specified.
M.O. 2018-01, s. 30.